Answer in brief

The most common mistakes in a walk me through a DCF answer are mixing levered and unlevered pieces, calling the result equity value when it is enterprise value, skipping the bridge to equity, discounting the terminal value for the wrong number of years and using a perpetual growth rate above the economy's. Each one below has what it sounds like, why it is wrong and the sentence to say instead. Superday AI grades written DCF answers against a rubric and asks follow-up questions, so you can test these fixes before the real interview.

Where a mistake changes the number, the size of the error comes from the worked example, which values Example Co. at an enterprise value of $2,648.7 million and $19.99 a share.

Mixing the cash flow and the discount rate

Discounting unlevered free cash flow at the cost of equity

What it sounds like: "Then I discount the free cash flows at the cost of equity."

Why it is wrong: Unlevered free cash flow belongs to lenders and shareholders together, so it needs a rate that blends both of their returns. The cost of equity only fits levered free cash flow, which is what is left for shareholders after interest and debt repayment.

Say instead: "Because the cash flows are unlevered, I discount at WACC."

Subtracting interest from unlevered free cash flow

What it sounds like: "EBIT, less interest and taxes, plus D&A..."

Why it is wrong: Taking out interest turns the cash flow into a levered one, and then WACC counts the cost of debt a second time. Taxes in unlevered free cash flow are on EBIT, as if the company had no debt.

Say instead: "I tax EBIT directly to get NOPAT. Interest stays out because the cost of debt is already in WACC."

Using the pre-tax cost of debt

What it sounds like: "Cost of debt is the yield on their bonds."

Why it is wrong: Interest is deductible, and since unlevered free cash flow ignores that tax saving, WACC has to pick it up. At a 6% yield and a 25% tax rate the cost to use is 4.5%.

Say instead: "Cost of debt is the current yield, times one minus the tax rate."

Getting the cash flow wrong

Calling EBITDA minus capex free cash flow

What it sounds like: "Free cash flow is EBITDA minus capex."

Why it is wrong: It leaves out taxes and working capital. For Example Co. in 2027, EBITDA minus capex is 264.0 minus 55.0, which is 209.0, against true unlevered free cash flow of 144.0.

Say instead: "EBIT times one minus the tax rate, plus D&A, minus capex, minus the increase in net working capital."

Getting the working capital sign backwards

What it sounds like: "Plus the change in working capital."

Why it is wrong: When working capital grows, cash is tied up in inventory and receivables, so an increase reduces free cash flow. Only a decrease adds cash.

Say instead: "Minus the increase in net working capital."

Getting from enterprise value to a share price

Calling the sum equity value

What it sounds like: "Add up the discounted cash flows and the terminal value, and that's the equity value."

Why it is wrong: Discounting unlevered cash flow at WACC gives enterprise value, the value to every capital provider. Dividing that by shares for Example Co. gives $26.49 a share instead of $19.99, about a third too high.

Say instead: "The sum is enterprise value. Then I bridge to equity value."

Stopping at "subtract debt"

What it sounds like: "Then subtract the debt and divide by shares."

Why it is wrong: Cash gets added back, and other claims ahead of common shareholders come out too. Preferred stock and noncontrolling interest are the usual ones, and equity investments not in the cash flows get added.

Say instead: "Subtract debt, preferred and noncontrolling interest, add cash and investments, and that's equity value."

Dividing by basic shares

What it sounds like: "Divide by shares outstanding."

Why it is wrong: Options, restricted stock and convertible securities that would turn into shares also have a claim on the equity value. If Example Co.'s 100 million diluted shares were 96 million basic, using basic would show $20.82 instead of $19.99.

Say instead: "Divide by diluted shares, using the treasury stock method for options."

Getting the terminal value wrong

Discounting the terminal value the wrong number of years

What it sounds like: "Then I discount the terminal value back one more year than the last cash flow." Or not discounting it at all.

Why it is wrong: The terminal value is a value at the end of the last projected year, so it takes the same discount factor as that year's cash flow. For Example Co., discounting it six years instead of five cuts enterprise value to $2,484.0 million, 6.2% too low. Not discounting it at all gives $3,723.0 million, 40.6% too high.

Say instead: "The terminal value is as of the end of year five, so I discount it five years."

A perpetual growth rate above the economy's

What it sounds like: "I'd grow it at 6% in the terminal period, since that's what it grew at in the projection."

Why it is wrong: No company can grow faster than the economy forever. And as growth nears WACC the formula runs away. At a 9% WACC, Example Co.'s enterprise value goes from $2,648.7 million at 2.5% growth to $5,123.1 million at 6%. At or above 9% the formula stops giving a usable number at all.

Say instead: "Something near long-run inflation, 2 to 3 percent, and well below WACC."

Putting an equity multiple on the terminal year

What it sounds like: "For the exit multiple I'd use a P/E from comparable companies."

Why it is wrong: A P/E multiple on net income gives equity value. Adding that to the present value of unlevered cash flows mixes an equity value into an enterprise value.

Say instead: "An EV to EBITDA multiple on final-year EBITDA, since this is an unlevered DCF."

Delivery

Starting with WACC and never getting to the end

What it sounds like: Two minutes on CAPM and beta before a cash flow has been mentioned.

Why it is wrong: The interviewer asked for the walk-through, and the order of the bridge is part of the answer. Spending the time on one input means the terminal value and the bridge get rushed or dropped.

Say instead: Give all four steps once at the length on the home page, then let the interviewer choose where to go deeper. The likely places are on the follow-ups page.

Questions and answers

Which DCF mistake costs the most in an interview?

Mixing levered and unlevered pieces, such as discounting unlevered free cash flow at the cost of equity. It shows the logic of the method has not landed, and interviewers tend to stop and probe it.

Is it a mistake to give the 5-minute answer?

Only when nobody asked for it. A long answer to a short question uses time the interviewer wanted for follow-ups, and the risk of saying something wrong grows with every extra sentence.